Overview

This project will extend light rail to the Eastridge Transit Center with elevated structures at Capitol Avenue, Story Road, and Tully Road. The Eastridge extension will include LRT stations at Story Road and at the Eastridge Transit Center.

Background

Capitol Expressway Light Rail to Eastridge is part of the larger Capitol Expressway Transit Improvement Project that transforms Capitol Expressway into a multi-modal boulevard offering bus rapid transit (BRT), light rail transit, and safe connections to the regional transit system.  VTA first addressed pedestrian access and improved safety measures along the expressway between Quimby Road and Capitol Avenue.  This was completed in Fall 2012 and included new sidewalks, street lighting, and a landscaping buffer.  Next was the reconstruction of the Eastridge Transit Center which was completed in 2015. The last portion will extend light rail from the existing Alum Rock Light Rail Station to the Eastridge Transit Center. 

(click for full size image)

Project Status

  • ​In June 2016 VTA Board of Directors approved funding to complete design, acquire right of way and relocate utilities.
  • Construction is dependent on Board of Directors approval of funding/financing plan.

Project Schedule

  • 2016-2017 Environmental Studies
  • 2016-2018 Right of Way
  • 2017-2018 Utility Relocation
  • 2019-2022 Construction*
  • *Contingent upon funding availability

Project Cost

$377 Million for design, right of way, utilities and construction. 
 