Capital Program Dashboard

Capital Program Dashboard

As of 3/31/2016
Project Locations (All Programs)
* Projects classified as Systemwide are not reflected on the map.

To see a project name, zoom in and hover over a locator on the map above. For details on the project click the link.

Project Locations (VTA Transit)
* Projects classified as Systemwide are not reflected on the map.

To see a project name, zoom in and hover over a locator on the map above. For details on the project click the link.

Current Appropriation by Category (VTA Transit)
Projects By Phase (VTA Transit)
Current Appropriation by Project Type (VTA Transit)

Project Details (VTA Transit) Data Download Report Glossary
Budget Schedule
Project Name Photos Phase Original Cost Estimate Current Cost Estimate Original Estimate vs. Current Current Appropriation Scope Change Original Start Current Start Original Completion Current Completion
Revenue Vehicles & Equipment
Kinkysharyo LRV Overhaul Program Procurement $23,010,000 $11,906,400 -48% $11,906,400 Jun-12 Jun-11 Jun-21 May-17
Express Bus Vehicle Purchase Procurement $14,000,000 $16,120,000 15% $16,120,000 Jun-11 Jun-11 Jul-13 Mar-16
Purchase Community Buses Completed $10,125,000 $25,641,000 153% $25,641,000 Jun-11 Mar-12 Jun-13 Jun-16
Paratransit Vehicles and Equipment Planning $3,475,650 $3,475,650 0% $3,475,650 Jun-12 Jun-12 Dec-15 Dec-16
40' Bus Procurement Procurement $172,000,000 $45,133,211 -74% $45,133,211 Jun-13 Jun-13 Jun-17 Jun-17
60' Articulated Bus Procurement Design $52,214,000 $76,461,618 46% $60,747,428 Jun-13 Jun-13 Jun-15 Jun-19
Automatic Passenger Counters LR Vehicles Design $1,450,000 $1,450,000 0% $1,450,000 Oct-13 Jun-13 Mar-15 Jun-16
40' Bus Procurement FY16 Design $60,875,229 $60,875,229 0% $60,875,229 Jun-15 Jun-15 Jun-19 Jun-19
Wheelchair Ramp Replacement on 70 Buses Planning $1,050,000 $1,050,000 0% $1,050,000 Jun-15 Jun-15 Feb-16 Jun-16
Light Rail Vehicle CCTV Upgrade Planning $5,500,000 $5,500,000 0% $5,500,000 Dec-16 Dec-16 Dec-17 Jan-18
3-Position Exterior Bike Racks for Buses Planning $900,000 $900,000 0% $900,000 Jul-15 Jun-15 Jun-16 Jun-16
LR Vehicle CCTV Door Monitoring System Planning $1,000,000 $1,000,000 0% $1,000,000 Jun-15 Jun-15 Dec-16 Dec-16
Electric Bus Pilot Project Planning $4,000,000 $4,000,000 0% $4,000,000 Jul-15 Jun-15 Aug-17 Sep-17
Tire Barrier Retrofit Planning $625,000 $625,000 0% $625,000 Aug-15 Jun-15 May-16 Jun-17
Passenger Facilities
Tamien Station Parking Structure Design $400,000 $225,000 -44% $225,000 increase icon Feb-05 Dec-13 Sep-06 Dec-19
High Volume Bus Stop Improvement Design $2,750,000 $1,900,000 -31% $1,900,000 Jul-12 Aug-12 Jul-13 Oct-18
Ped Swing Gates Replacement Planning $370,000 $1,450,000 292% $1,450,000 increase icon Jun-12 Sep-12 Nov-13 Dec-17
Bus Stop Pavement/Duckout Improv. FY14 Construction $1,044,500 $1,044,500 0% $1,044,500 Jun-13 Jun-13 May-15 Oct-16
Infrastructure-Add'l ClipperFare Devices Construction $550,000 $550,000 0% $550,000 Jun-13 Jun-13 Jun-15 Feb-17
Emergency Power Generators Design $400,000 $1,200,000 200% $1,200,000 Jun-13 Jun-13 Jun-15 Mar-18
Tasman Station Repair Design $300,000 $300,000 0% $300,000 Jan-15 Jan-15 Dec-16 Sep-17
RTI Signs at Light Rail Stations Construction $869,500 $869,500 0% $869,500 Feb-15 Feb-15 Dec-16 Feb-17
LR Facilities LED Lighting Retrofit Planning $937,500 $937,500 0% $937,500 Jun-15 Jun-15 Jun-16 Dec-17
Bus Stop Pavement/Duckout Improv. FY16 Planning $962,096 $962,096 0% $962,096 Jun-16 Jun-16 Jun-18 Jun-18
Ticket Vending Machines - Stadium Events Design $660,000 $660,000 0% $660,000 Jun-15 Jun-15 Jan-16 Sep-16
Light Rail Station Signage Replacement Planning $2,000,000 $2,000,000 0% $2,000,000 Jun-15 Jun-16 Aug-17 Feb-18
Transit Center Park & Ride Upgrades FY16 Planning $500,000 $500,000 0% $601,821 Jun-15 Jun-15 Jun-17 Dec-17
Vasona Corridor Pedestrian Back Gates Planning $1,300,000 $1,300,000 0% $1,300,000 Jun-15 Jun-15 Jun-17 Sep-18
Diridon Sta. Intermodal Conceptual Plan Planning $1,000,000 $1,000,000 0% $1,000,000 Dec-16 Jan-16 Dec-17 Dec-17
Operating Facilities & Equipment
HazMat/Fac. Design and Construction Close-out $466,671 $264,344 -43% $264,344 decrease icon Sep-05 Nov-02 Oct-06 Dec-16
Bus Signal Priority Construction $929,719 $911,042 -2% $911,042 Jun-06 Jun-07 Nov-07 Dec-16
Green Facility Improvements Construction $5,200,000 $6,200,000 19% $6,200,000 Jun-07 Jun-07 Jun-15 Jun-17
Pavement Management Program-FY09 Design $716,928 $716,928 0% $716,928 increase icon Jun-08 Jun-08 Jun-09 Dec-17
SCADA System Hardening Construction $3,802,491 $4,233,554 11% $4,233,554 increase icon Mar-11 Mar-11 Mar-13 Dec-16
GFCI (switchgear) Testing & Replacement Design $212,175 $312,175 47% $312,175 increase icon Jun-11 Apr-11 Jun-13 Mar-18
HVAC Replacement Program FY12 & FY13 Construction $1,176,500 $1,176,500 0% $1,176,500 Jun-11 Jun-11 Jun-13 Jun-16
Fac.Maint. Equipment Program FY12 & FY13 Construction $788,370 $788,370 0% $788,370 Jun-11 Sep-11 Jun-13 Jun-16
LRV Body Shop-Dust Separation Wall Design $545,000 $1,045,000 92% $1,045,000 increase icon Jun-13 Oct-11 Jun-14 Dec-17
LRV Maintenance Shop Hoist Design $3,437,320 $5,051,370 47% $5,051,370 increase icon Jun-13 Oct-12 Jun-14 Dec-17
River Oaks Auditorium & Lobby Reconfig Close-out $500,000 $555,000 11% $555,000 increase icon Jun-12 Jun-12 Jun-13 Sep-16
Radio System Installation FY13 Construction $1,300,000 $454,488 -65% $454,488 Jun-12 Jun-12 Mar-14 May-16
Downtown Customer Service Ctr.Move(2013) Close-out $576,950 $967,117 68% $967,117 increase icon Jan-13 Feb-13 Jul-13 Jun-16
Replace Wheel Turning Machine Planning $2,600,000 $2,600,000 0% $2,600,000 Jun-13 Jun-13 Jun-15 Jun-19
LED Exterior Lighting Replacement Design $900,000 $900,000 0% $900,000 Dec-14 Jun-13 Dec-15 Mar-17
Cerone Propane Tank Replacement Design $350,000 $350,000 0% $350,000 Jun-14 Jun-13 Jun-15 Dec-17
Facilities Maint. Equipment Program FY14 Design $1,125,900 $1,125,900 0% $1,125,900 Jun-13 Jun-13 Jun-15 Jun-16
Paving Management Program FY14 Construction $2,316,000 $2,316,000 0% $2,316,000 Jun-13 Jun-13 Jun-15 Dec-16
Cerone Boiler Replacement Design $300,000 $300,000 0% $300,000 Jun-13 Jun-13 Aug-14 Dec-17
Cerone Emergency Generator Replacement Design $1,200,000 $1,200,000 0% $1,200,000 Jun-14 Jun-13 Jun-15 Dec-17
HVAC Replacement Program FY14 Design $550,800 $550,800 0% $550,800 Jun-13 Jun-13 Jun-15 Dec-16
Roofing Management Program FY14 Design $900,000 $900,000 0% $900,000 Jun-13 Jun-13 Jun-15 Jun-16
Painting Management Program FY14 Construction $1,000,000 $1,000,000 0% $1,000,000 Jun-13 Jun-13 Jun-15 Dec-16
LR Signal Shop Modification Planning $495,000 $495,000 0% $495,000 Jun-13 Jun-15 May-14 Jun-18
CCTV Surveillance Equipment Construction $2,144,129 $3,243,000 51% $3,086,403 increase icon Apr-14 Apr-14 Mar-16 Dec-16
CCTV Equipment Planning $1,500,000 $3,336,000 122% $3,336,000 Sep-14 Sep-14 Mar-17 Jun-17
Cerone Fuel Island Modular Building Procurement $54,000 $110,000 104% $110,000 increase icon Jun-15 Mar-15 Dec-16 Jun-16
OCC Rail control Reconfiguration Construction $100,000 $150,000 50% $150,000 increase icon May-15 May-15 Dec-16 Jun-16
Guadalupe SCADA & OCC UPS Replacement Procurement $105,413 $105,413 0% $105,413 Mar-15 Apr-15 Mar-16 Jun-17
Automated Wheel Measurement Sys LR Veh. Planning $878,750 $878,750 0% $878,750 Aug-15 Jun-15 Jun-18 Jun-18
Guadalupe Train Wash Replacement Planning $1,810,000 $1,810,000 0% $1,810,000 Jun-15 Jun-15 Jun-17 Dec-19
Facilities Maint. Equipment Program FY16 Planning $949,212 $949,212 0% $949,212 Jun-15 Jun-15 Jun-17 Dec-16
HVAC Replacement Program FY16 Planning $1,300,000 $1,300,000 0% $1,300,000 Jun-15 Jun-15 Jun-17 Jun-17
Pavement Management Program FY16 Planning $910,000 $910,000 0% $910,000 Jun-15 Jun-15 Jun-17 Dec-17
Painting Management Program FY16 Planning $1,540,000 $1,540,000 0% $1,540,000 Jun-15 Jun-15 Jun-17 Mar-18
Roofing Management Program FY16 Planning $923,000 $923,000 0% $923,000 Jun-15 Jun-15 Jun-17 Dec-17
Chaboya Yard Well Removal Planning $245,000 $245,000 0% $245,000 Jun-15 Jun-15 Jun-16 Dec-17
Employee Facility Updates at Chaboya Planning $533,000 $533,000 0% $533,000 Jun-15 Jun-15 Jun-17 Dec-17
River Oaks Parking Lot Improvement Proj. Construction $175,000 $270,000 54% $270,000 Sep-15 Aug-15 Oct-15 Dec-16
Enhanced CCTV Sys-Major Events Hardening Construction $1,897,488 $1,897,488 0% $1,897,488 Sep-15 Oct-15 Feb-16 Mar-17
Non-Revenue Vehicles
NRV Procurement Project Procurement $1,931,430 $1,931,430 0% $1,931,430 Jun-11 Jun-11 Jun-13 Jun-16
Non-Revenue Vehicle Procurement FY14 Design $1,071,600 $1,071,600 0% $1,071,600 Jun-13 Jun-13 Jun-15 Dec-16
Non-Revenue Vehicle Procurement FY16 Planning $863,200 $863,200 0% $863,200 Jun-15 Sep-15 Jun-17 Jun-17
Miscellaneous
VETS Transpt.& Community Living Initiat. Design $2,050,000 $2,050,000 0% $2,050,000 Jul-12 Jun-13 Dec-14 Dec-16
Core Connectivity Study Planning $320,000 $320,000 0% $320,000 Feb-15 Feb-15 Jun-17 Nov-17
Slow Speed Zone Study Planning $300,000 $300,000 0% $300,000 Mar-15 May-15 Dec-17 Mar-17
Caltrain Capital-Local Match FY16 & FY17 Construction $7,860,000 $10,000,000 27% $10,000,000 Jun-15 Jun-15 Jun-17 Jun-17
Small Business Sustainability Program Ongoing $1,500,000 $1,500,000 0% $1,500,000 Nov-15 Nov-15 Mar-16 Apr-16
Light Rail Way, Power & Signal
Cooling Sys.for LRSignal/Commun.Cabinets Procurement $314,291 $314,291 0% $314,291 Jun-07 Jun-10 Jun-08 Jan-16
Rail Replacement & Rehab Construction $20,673,908 $20,673,924 0% $20,673,924 increase icon Jun-09 Feb-09 Jun-20 Dec-17
Traction Power Substation Procurement Design $17,379,385 $20,259,715 17% $20,259,715 increase icon Jun-10 Sep-09 Jun-19 Aug-18
Guada.OCS Rehab & Replacement Program Design $29,103,546 $9,075,576 -69% $9,075,576 decrease icon Jun-10 Jun-09 Jun-20 Jun-18
LRT Crossovers and Switches Design $3,448,773 $3,448,773 0% $3,448,773 Jun-14 Jun-11 Jun-17 Dec-17
Bridge Repair/Hamilton Struct.Stabilizat Planning $1,700,000 $2,400,000 41% $2,800,000 increase icon Jun-11 Mar-12 Dec-14 Jun-17
Guada Signal Assessment/SCADA Sys Replac Design $20,000,000 $3,500,000 -82% $3,500,000 decrease icon Jun-12 Jun-12 Jun-17 Oct-17
N 1st & DT SJ LR Speed Improvmt Design Design $3,832,000 $1,162,000 -70% $1,537,000 Dec-11 Apr-12 Oct-12 Dec-16
Update Santa Teresa Interlock Sig. House Construction $860,000 $2,160,000 151% $2,160,000 increase icon Jun-11 Jun-12 Jun-14 Sep-16
LR Transit Signal Priority Improvements Procurement $1,792,813 $1,792,813 0% $1,792,813 Aug-12 Aug-12 Sep-13 Oct-17
Upgrade Ohlone/Chynoweth Interlocking Planning $1,200,000 $1,200,000 0% $1,200,000 Jun-13 Jun-13 Dec-16 Dec-19
Track Intrusion Abatement FY14 Planning $2,000,000 $2,000,000 0% $2,000,000 Jun-13 Jun-13 May-15 Jun-18
Addt'l TractionPowerSubsta.@MountainView Construction $3,500,000 $3,500,000 0% $3,885,000 Dec-14 Dec-14 Dec-16 Dec-16
SCADA Rehabilitation Construction $2,040,763 $4,104,763 101% $2,040,763 Jun-15 Jun-15 Jun-16 Dec-16
Downtown San Jose Speed Improvement-Ph1 Design $6,000,000 $5,000,000 -17% $5,000,000 Dec-16 Jun-16 Dec-17 Jun-18
Light Rail Crossovers and Switches FY16 Planning $8,200,000 $4,100,000 -50% $4,100,000 Jun-16 Jun-15 May-19 Sep-19
Rail Rehabilitation & Replacement FY16 Planning $4,500,000 $4,500,000 0% $4,500,000 Jun-16 Jun-16 Mar-19 Sep-19
Traction Power Substa Procurement FY16 Planning $9,000,000 $9,000,000 0% $9,000,000 Jun-16 Jun-16 Dec-18 Jun-19
Bridge and Structure Repairs FY16 Planning $1,500,000 $700,000 -53% $700,000 Jun-15 Nov-15 Jun-17 Dec-19
Track Intrusion Abatement FY16 Planning $2,000,000 $2,000,000 0% $2,000,000 Jun-16 Jun-15 Jun-18 Dec-19
Traction/Substation Power Monitoring Sys Planning $234,542 $234,542 0% $234,542 Jun-15 Jun-15 Jun-16 Mar-17
Emergency Rail Rehab @ Younger Avenue Completed $100,000 $100,000 0% $100,000 Dec-16 Dec-16 Mar-16 Dec-16
Information Sys & Technology
SCADA GEisys Software Upgrade Planning $1,250,000 $1,250,000 0% $1,250,000 Jun-11 Jun-11 Jun-12 Jun-18
Trapeze OPS Software Installation Construction $3,200,000 $3,200,000 0% $3,200,000 Sep-11 Oct-11 Sep-13 Jun-16
VTA Gigabit Network Project Construction $1,425,000 $1,425,000 0% $1,425,000 Jun-11 Jun-11 Mar-13 Aug-17
Record Management Program Construction $2,788,000 $2,788,000 0% $2,788,000 Dec-11 Jul-12 Dec-16 Mar-17
Train to Wayside Communicat. Sys Upgrade Planning $250,000 $1,605,750 542% $1,605,750 Jun-13 Jun-13 Dec-16 Jun-18
TERM Lite Deployment Construction $600,000 $400,000 -33% $400,000 Dec-14 Dec-14 Dec-15 Dec-16
SAP Plant Maint. & Materials Management Design $300,000 $300,000 0% $300,000 Dec-14 Jun-13 Dec-15 Dec-16
Bus. Process Automation - Acts. Payable Construction $455,000 $657,000 44% $732,000 Aug-14 Oct-14 Mar-15 Oct-16
Upgrade Countywide Travel Demand Model Planning $650,000 $650,000 0% $650,000 Jun-13 Jun-13 Jun-15 Jan-17
Telecommunications System Updates Construction $375,000 $375,000 0% $375,000 Jun-13 Jun-13 Jun-15 Feb-17
CAD-AVL Update Design $7,000,000 $7,000,000 0% $4,959,237 Jun-13 Jun-13 Jun-15 Dec-20
Upgrade LR Ring #1 Communications Equip. Planning $2,200,000 $2,200,000 0% $2,200,000 Oct-14 Jun-13 Oct-15 Sep-18
Radio System Upgrade Construction $2,500,000 $4,850,000 94% $4,850,000 Jun-13 Jun-13 Jun-15 Dec-16
Business Process Automation - Payroll Construction $295,000 $663,000 125% $663,000 Feb-14 Feb-14 Dec-15 Nov-16
Implement Talent Management Solution Construction $325,000 $325,000 0% $325,000 Dec-15 Mar-15 Jun-15 Nov-16
Mobile Network-Full Fleet Wi-Fi Construction $650,000 $650,000 0% $650,000 Jun-14 Sep-14 Sep-15 Feb-17
CCTV Emergency Storage Expansion Construction $175,000 $175,000 0% $175,000 Oct-14 Oct-14 Jan-15 Jun-16
Interactive Customer Message Boards Construction $690,000 $690,000 0% $690,000 Nov-14 Nov-14 Jun-17 Jun-17
Multimodal TripDataCollector/Planner APP Design $125,000 $275,000 120% $275,000 increase icon Jan-15 Jan-15 Jun-15 Jun-16
Demand Response & Subscription Solution Procurement $400,000 $400,000 0% $400,000 Jan-15 Jan-15 Sep-15 Oct-17
Network and Gigabit Fiber Upgrade Construction $700,000 $700,000 0% $700,000 Jun-15 Jun-15 Jun-16 May-17
SCADA Programming Planning $1,100,000 $1,100,000 0% $1,100,000 Jun-15 Jun-15 Dec-16 Dec-17
Server Refresh Procurement $500,000 $500,000 0% $500,000 Jun-15 Jun-15 Jun-16 Feb-17
CreditCard Authorization Sys Enhancement Planning $180,000 $180,000 0% $180,000 Jun-15 Jun-15 Jun-17 Jun-17
GIS Program Development Construction $250,000 $250,000 0% $250,000 Jun-15 Jun-15 Jun-17 Jun-17
Server Security Repl/Performance Upgrade Design $1,050,000 $1,050,000 0% $1,050,000 Jun-15 Jun-15 Jun-16 Jun-17
Electr.Procure./Contract Bidding Process Planning $210,000 $210,000 0% $210,000 Dec-16 Jun-16 Jul-17 Jul-17
Connected Vehicles Technology Platform Planning $1,000,000 $1,000,000 0% $1,000,000 Jun-15 Jun-15 Dec-16 Dec-16
Cal Cloud Network and Server Upgrade Design $900,000 $900,000 0% $900,000 Jun-15 Jun-15 Jun-17 Jun-17
Dynamic Transit Pilot Service Planning $2,000,000 $2,000,000 0% $2,000,000 Jun-15 Jun-15 Jun-17 Jun-17
Project/Construction Management Software Planning $325,000 $325,000 0% $325,000 Jan-16 Dec-16 Dec-16 Dec-16
Project Locations (2000 Measure A)
* Projects classified as Systemwide are not reflected on the map.

To see a project name, zoom in and hover over a locator on the map above. For details on the project click the link.

Current Appropriation by Category (2000 Measure A)
Projects By Phase (2000 Measure A)
Current Appropriation by Project Type (2000 Measure A)

Project Details (2000 Measure A) Data Download Report Glossary
Budget Schedule
Project Name Photos Phase Original Cost Estimate Current Cost Estimate Original Estimate vs. Current Current Appropriation Scope Change Original Start Current Start Original Completion Current Completion
SVRT Program
Berryessa Extension Project - SVBX Construction $2,421,273,000 $2,421,272,972 0% $2,129,067,705 Dec-10 Jan-10 Jun-18 Jun-19
20 Non New Starts BART Vehicles Design $82,500,000 $83,985,221 2% $83,985,221 Dec-11 Mar-12 Dec-16 May-19
BART HMC and ROW (excl. HYPSC) Construction $136,100,000 $135,000,000 -1% $134,494,424 Dec-11 Dec-11 Jun-18 Jun-21
Montague Reconstruction Project Construction $17,051,000 $21,969,513 29% $21,969,513 increase icon Mar-13 May-13 Jun-18 Mar-18
BART Core System Modifications Design $46,000,000 $46,000,000 0% $32,012,245 Jun-13 Jun-13 Jun-18 Dec-19
Upper Penitencia Creek Trail Connector Construction $2,415,100 $2,457,087 2% $2,457,087 Oct-13 Oct-13 Dec-16 Jun-17
Montague Exwy POC Design Design $844,000 $844,000 0% $844,000 Sep-15 Sep-15 Jun-17 Dec-19
FRR-Lower Berryessa Creek - VTA Close-out $5,600,000 $5,999,523 7% $5,999,523 Jun-08 Jan-07 Dec-11 Dec-16
MWT Project Close-out $137,895,519 $143,237,862 4% $145,063,290 May-09 Dec-05 Dec-14 Dec-16
LBC Project (C210) Close-out $34,128,000 $34,152,350 0% $34,152,350 Oct-08 Jan-07 Dec-11 Dec-16
SVRT Project Development After FY09 Planning $4,700,000,000 $4,700,000,000 0% $123,446,017 May-09 Jun-09 Dec-26 Jun-27
Light Rail Program
New Rail Corridors Study Planning $1,300,000 $1,459,401 12% $1,459,401 Feb-05 Dec-05 Feb-07 Jun-17
LRT Extension to Vasona Junction Planning $106,076,000 $176,000,001 66% $12,915,660 increase icon Jun-07 Jun-09 Jun-12 Mar-36
CELR - Eastridge Transit Center Construction $51,046,000 $60,703,790 19% $71,109,928 increase icon Jun-09 Oct-10 Jun-14 Dec-16
Northern Light Rail Express Construction $34,850,000 $63,243,569 81% $65,209,438 increase icon Feb-11 May-12 Dec-18 Dec-16
CELR - Ph.II - LRT to Eastridge Planning $390,558,856 $376,900,000 -3% $20,000,000 decrease icon Jun-12 Jun-06 Jun-18 Mar-36
Santa Clara Pocket Track Close-out $10,000,000 $26,895,995 169% $29,571,396 increase icon Jun-13 Jun-13 Jun-15 Jun-17
N.1st Speed Improve. & 1st/Tasman Mods Design $7,000,000 $7,000,000 0% $7,000,000 Dec-16 Jun-16 Dec-17 Jun-18
Winchester LR Line Dbl Trk & Pltform Ext Planning $2,000,000 $2,000,000 0% $2,000,000 Dec-16 Jun-16 Dec-17 Jun-17
Commuter Rail Program
SC Sta. Pedestrian Underpass Extension Design $7,000,000 $13,725,775 96% $13,727,460 increase icon Mar-07 Jun-08 Jul-09 Dec-17
Caltrain Electrification Engineer Review Planning $2,800,000 $1,310,887 -53% $1,310,899 Jun-09 Jun-09 Jun-13 Dec-36
Caltrain Electrification Invest. Program Ongoing $60,000,000 $60,133,999 0% $60,133,999 Jun-13 Dec-12 Jun-22 Jun-20
Caltrain Safety Enhancements Design $8,000,000 $31,414,722 293% $31,414,770 increase icon Feb-07 May-07 Jun-12 Dec-17
Bus Program
Alum Rock/Santa Clara BRT Project Construction $127,600,000 $127,335,512 0% $127,608,518 decrease icon Jun-09 Dec-08 Jun-12 Dec-17
Stevens Creek BRT Project Planning $188,860,724 $7,604,301 -96% $7,606,398 decrease icon Apr-11 Jun-09 Oct-12 Dec-17
El Camino Real BRT Planning $216,000,000 $46,199,420 -79% $46,199,420 Dec-11 Jun-09 Jan-14 Jun-17
Procurement of BRT Articulated Buses Procurement $48,000,000 $57,619,195 20% $57,653,195 Dec-11 Jun-09 Jan-16 Jun-18
King Road BART BRT Planning $1,051,000 $3,022,629 188% $3,022,629 decrease icon Sep-11 Jun-11 Oct-12 Dec-36
Mod.of Chaboya & North Div.for BRT Buses Planning $12,830,950 $14,381,277 12% $14,406,880 increase icon Jun-12 Jun-12 Mar-14 Dec-17
BART Transit Integration Analysis Planning $2,000,000 $834,789 -58% $834,789 increase icon Jun-13 Jun-13 Jun-15 Dec-17
De Anza College Transit Ctr Improvements Planning $10,000,000 $10,000,000 0% $10,000,000 Nov-15 Jun-15 Oct-16 Jun-21
Project Locations (VTP Highway)
* Projects classified as Systemwide are not reflected on the map.

To see a project name, zoom in and hover over a locator on the map above. For details on the project click the link.

Projects By Phase (VTP Highway)
Current Appropriation by Project Type (VTP Highway)

Project Details (VTP Highway) Data Download Report Glossary
Budget Schedule
Project Name Photos Phase Original Cost Estimate Current Cost Estimate Original Estimate vs. Current Current Appropriation Scope Change Original Start Current Start Original Completion Current Completion
Highway
I-880/I-280 Improvements(Stevens Creek) Close-out $110,000,000 $65,965,842 -40% $65,965,842 decrease icon Jun-07 Dec-02 Dec-14 Dec-16
US101 Dela Cruz Blvd/Trimble Rd IC Impro Planning $800,000 $4,953,600 519% $4,953,600 Dec-05 May-06 Dec-06 Jul-20
SR 152 Realignment Planning $450,000,000 $31,390,189 -93% $31,390,189 Jun-09 Apr-07 Jun-13 Dec-19
I-680 Corridor Study Planning $2,000,000 $500,000 -75% $500,000 Jun-07 Dec-08 Jun-08 Mar-16
Rt 87/Narvaez Interchange Planning $800,000 $800,000 0% $800,000 Jun-07 Dec-11 Jun-08 Dec-20
Ramp Metering Implementation Construction $3,500,000 $11,787,500 237% $11,787,500 Jun-07 Aug-08 Jun-08 Dec-16
Rt 237/Rt 101 Mathilda Interchange Planning $25,000,000 $35,846,757 43% $35,846,757 Jun-08 May-09 Jun-16 Jul-19
Silicon Valley Express Lanes - SR 85 Close-out $181,200,000 $7,440,000 -96% $7,440,000 Jun-09 Jun-09 Jun-15 Apr-16
Silicon Valley Express Lanes - US 101 Close-out $425,000,000 $8,980,000 -98% $8,980,000 Apr-11 Apr-11 Jun-17 Feb-16
US 101/Capitol Expwy/Yerba Buena Interch Close-out $40,000,000 $30,523,050 -24% $33,690,208 Mar-10 Apr-10 Dec-11 Dec-16
Freeway Performance Initiative–Design Ph Construction $7,562,500 $7,000,000 -7% $7,000,000 Jan-11 Aug-11 Jun-15 Aug-18
SR 237 Express Lanes-Phase II Extension Design $20,000,000 $20,067,492 0% $20,067,492 Dec-11 Mar-12 Dec-15 Dec-19
I-280/Foothill Expressway Ramp Improv. Planning $2,700,000 $3,200,000 19% $3,200,000 Jun-12 Mar-12 Jun-14 Jun-18
Combined Landscaping & Maint. Project Construction $3,722,000 $3,824,254 3% $3,824,254 Oct-12 Oct-12 Nov-16 Jun-20
101 Express Lanes - 101 San Mateo Planning $4,000,000 $2,000,000 -50% $2,000,000 Jun-13 Nov-16 Dec-19 Jun-18
Charcot Avenue Extension over I-880 Close-out $4,500,000 $100,000 -98% $100,000 Jun-13 Jun-13 Dec-16 Dec-16
Innovat. Transportation Technology Prog. Planning $7,000,000 $2,000,000 -71% $2,000,000 Jun-13 Jun-15 Dec-16 Jun-17
Intelligent Transportation System Proj. Planning $16,000,000 $14,000,000 -12% $14,000,000 Jun-14 Jun-14 Dec-16 Dec-17
Landscaping@ I-280/I-880/StevensCrk Blvd Design $3,500,000 $3,500,000 0% $3,500,000 Jun-13 Jun-13 Dec-16 Dec-20
US 101 / Buena Vista Avenue Planning $4,650,000 $4,000,000 -14% $4,000,000 Jun-14 Jun-17 Jun-16 Dec-21
US 101 SB Ramp Improv.10th St. in Gilroy Planning $3,600,000 $3,600,000 0% $3,600,000 Jun-13 Jun-13 Dec-16 Jun-16
Silicon Valley Express Lanes - I-880 Planning $35,000,000 $4,000,000 -89% $4,000,000 Jun-13 Jun-16 Dec-16 Jun-22
101 SB SanAntonio/Charleston/Rengstorff Planning $4,000,000 $4,000,000 0% $4,000,000 Dec-14 Jun-16 Dec-16 Dec-22
US 101/Old Oakland Road Improvements Planning $3,450,000 $3,450,000 0% $3,450,000 Jun-13 Jun-16 Dec-16 Dec-20
Capitol Expy-Ped Connection to Eastridge Design $1,547,400 $1,547,400 0% $1,547,400 Sep-14 Sep-14 Oct-18 Dec-17
SV Express Lanes-US101/SR85 PH 3 Design $35,800,000 $35,800,000 0% $35,800,000 Nov-14 Dec-15 Jun-19 Sep-20
SV Express Lanes-US101/SR85 PH 4 Design $11,400,000 $11,400,000 0% $11,400,000 Nov-14 Dec-15 Jun-19 Sep-20
SV Exp.Lanes-Electronic Toll System(ETS) Planning $47,221,000 $18,900,000 -60% $14,821,000 Dec-15 Feb-15 Jun-24 Jun-24
Noise Reduction Program on SR85 Planning $7,375,000 $2,375,000 -68% $2,375,000 Nov-14 Dec-15 Aug-19 Aug-19
I-280 Winchester Study Planning $671,000 $3,500,000 422% $3,500,000 Nov-14 Nov-14 Jun-17 Jun-17
I-280 Corridor Study Planning $750,000 $750,000 0% $750,000 Nov-14 Jan-15 Mar-16 Jun-17
Bicycle Safety Educat./Promotional Act. Planning $142,512 $142,512 0% $142,512 May-15 May-15 Jun-16 Jun-17
Local PDA Planning- Santa Clara Procurement $1,015,475 $1,015,475 0% $1,015,475 Jul-15 Jul-15 Dec-17 Dec-17
Keyes-Story St. Complete Corridor Study Planning $451,824 $451,824 0% $451,824 May-15 May-15 May-17 May-18
Freeway Performance Initiative Ph 2 Planning $2,000,000 $2,000,000 0% $2,000,000 Jun-15 Jun-16 Jun-16 Jun-18
SV Express Lanes-Future Phase Project A Planning $135,000,000 $15,000,000 -89% $15,000,000 Dec-16 Dec-16 Jun-23 Jun-23
SV Express Lanes-Future Phase Project B Planning $135,000,000 $15,000,000 -89% $15,000,000 Dec-16 Dec-16 Jun-23 Jun-23
US101/Zanker Rd/Skyport Dr/N 4th St Inte Planning $125,000,000 $8,000,000 -94% $8,000,000 Jun-15 Feb-16 Aug-21 Aug-21
SR 237 Improv - Lawrence Expway to US101 Planning $22,000,000 $2,000,000 -91% $2,000,000 Jun-15 Jun-16 Jun-22 Jun-22
I-280 Corridor Improv-Initiation Doc.Dev Planning $2,500,000 $2,500,000 0% $2,500,000 Nov-15 Feb-17 Jun-17 Aug-18
I-680 Corridor Improv-Initiation Doc.Dev Planning $2,500,000 $2,500,000 0% $2,500,000 Nov-15 Feb-16 Jun-17 Aug-17
I-680 Sound Walls Planning $4,459,000 $600,000 -87% $600,000 Jun-15 Jun-15 Jul-17 Sep-19
New Corridor Studies-SR87&237/I-880/SR17 Planning $2,000,000 $2,000,000 0% $2,000,000 Jun-15 Dec-16 Jun-17 Dec-18
Countywide Bicycle Plan Update Planning $700,000 $700,000 0% $700,000 Jun-15 Jun-15 Dec-16 Jun-18
Countywide Traffic Signal Coord. Study Planning $170,000 $170,000 0% $170,000 Sep-15 Jul-16 Jun-17 Feb-18
Tasman Dr Complete Street Corridor Study Planning $1,927,300 $1,159,000 -40% $1,159,000 Jan-16 Jan-16 Dec-19 Dec-19
Bascom Ave Complete StreetCorridor Study Planning $1,661,700 $987,800 -41% $987,800 Jan-16 Jan-16 Dec-19 Dec-19
I-280/Wolfe Rd Interchange Improv Proj Planning $64,400,000 $4,400,000 -93% $4,400,000 Dec-16 Jan-16 Dec-22 Dec-22