Estimated Project Costs and Schedule | Plans + Projects | Our Work

Estimated Project Costs and Schedule

Cost

Eastbound, peak-period vehicle lane $37 million
Bicycle/pedestrian path and related improvements $25 million
Planning, environmental review, design

$8 million

TOTAL $70 million

Schedule

Environmental approval (Completed) August 2016
Final design/construction permit (Completed) August 2016
Construction begins October 2016
Third eastbound traffic lane project completion October 2017
Bicycle/pedestrian path project completion April 2018