Cost
Eastbound, peak-period vehicle lane | $37 million |
Bicycle/pedestrian path and related improvements | $25 million |
Planning, environmental review, design |
$8 million |
TOTAL | $70 million |
Schedule
Environmental approval (Completed) | August 2016 |
Final design/construction permit (Completed) | August 2016 |
Construction begins | October 2016 |
Third eastbound traffic lane project completion | October 2017 |
Bicycle/pedestrian path project completion | April 2018 |